Abstract Abstract: Recently, Wu Xinxiong, deputy director of the National Development and Reform Commission, said that the policy has been slowed down and the photovoltaic industry has once again become the focus of the market. However, for the domestic PV application market, the effects of these policies that have been introduced in a short period of time are still limited. From distributed photovoltaic...
Abstract: Recently, Wu Xinxiong, deputy director of the National Development and Reform Commission, said that the policy has slowed down and the photovoltaic industry has once again become the focus of the market. However, for the domestic PV application market, the effects of these policies that have been introduced in a short period of time are still limited. From the introduction of the distributed photovoltaic power generation subsidy price to the announcement of the distributed photovoltaic power generation application demonstration zone, combined with the speech of Wu Xinxiong, deputy director of the recent Development and Reform Commission, the photovoltaic industry has once again become the focus of the market. However, for the domestic PV application market, the effects of these policies that have been introduced in a short period of time are still limited.
Financing is difficult to solve
It is reported that among the 18 first batch of national distributed photovoltaic power generation application demonstration zone projects announced, most of the projects have not been started for more than one month since the announcement. This is true of the demonstration areas with policy advantages, not to mention other areas that have not been included in the demonstration area nationwide.
In fact, whether it is a demonstration zone or a non-demonstration zone, financing issues have become the “roadblock†for these PV applications. At present, the price of photovoltaic modules is about 8 yuan / watt, which is calculated, the construction cost of a 1 megawatt enterprise-level application project is about 8 million, which is not a small number for many enterprises.
The China Development Bank is a financial support organization for distributed photovoltaic projects with clear policies. According to the “Opinions on Supporting Distributed Photovoltaic Power Financial Services†issued by the National Energy Administration and China Development Bank in August, CDB supports various types of distributed photovoltaic power generation projects built and operated in the form of “spontaneous use, surplus Internet access, and grid regulationâ€. It will focus on piloting innovative financial services, such as new energy demonstration cities, green energy counties, and distributed photovoltaic power generation application demonstration zones, and establish investment and financing institutions that cooperate with local governments to provide financial services for distributed photovoltaic power generation projects.
However, this document does not state the relevant loan conditions and specific interest rates. The insiders worry that in the actual operation process, it is difficult for SMEs to obtain loans preferentially in comparison with central enterprises and listed companies.
Shen Fuxin, secretary-general of Zhejiang Photovoltaic Association, said that from the recent speech of the National Development and Reform Commission, the future distributed photovoltaic power generation project will become the mainstream of photovoltaic applications. However, due to the long period of investment and recovery of distributed PV projects, generally 7 to 8 years, it is obviously not realistic to expect PV module companies to take the lead in promoting this.
Shen Fuxin believes that the ideal state is to have a third-party service organization to participate in the development, construction, operation and maintenance of distributed photovoltaic projects. Since the distributed PV project has a long return period, but the revenue is stable and the overall rate of return is high, the service organization can share the future benefits with the project owner after solving the high cost in the early stage of the project.
Approval process needs to be simplified
Even if there is not bad money, the "local tyrants" are willing to build distributed photovoltaic applications from their own pockets, waiting for their processing will still be very lengthy.
A person in charge of a PV module manufacturing company told reporters that he planned to build a 1.7 MW scale distributed power generation project on the roof of his own factory, but the complicated approval procedures made him feel helpless.
The person in charge showed the reporter a list of the procedures used in the operation of the approval. There are 19 procedures, including the approval procedures of the local Development and Reform Commission, the Provincial Development and Reform Commission, and the local power company.
So many procedures have significantly reduced the speed of construction of distributed PV applications. The person in charge said that if the approval system can be changed to a filing system, the speed of the promotion of distributed photovoltaic projects will be much faster.
Not only is the approval process of the company complicated, but individuals also face heavy approval if they want to build a photovoltaic power generation project on their roof.
Chen Jilin, the first person in Shanghai to get a PV power purchase fee, told reporters that after his own affairs were reported by the media, there were more friends around him, but there were fewer implementations. Many of them were scared off by the troublesome approval process. It is understood that Chen Jilin's personal photovoltaic power generation project was implemented under the simplified process of the local power company, which is a case. In fact, the approval process for individual PV projects remains to be simplified.