Pneumatic Conveyor Unit Operation Procedures
1. Single-manipulation transfer: When commissioning or when it is not used for a long time, a separate test machine should be performed for each piece of equipment. The operating rules for stand-alone equipment are found in its instructions.
2. Air conditioning test: After confirming that each equipment is operating normally, it can be commissioned by the empty machine. The empty machine commissioning sequence is: the air compressor is finally opened, and all equipment is opened and the air source is opened.
3, with the material debugging: After the air conditioning test is normal, can only take the material test machine, the first small flow debugging, according to the situation slowly increase the flow, just start running, flow control in the design of 80%, wait for a period of time, all The equipment is adjusted to 100% after normal running.
4, operating under normal conditions
4.1 Starting sequence: From the discharge end to the feed end one by one, and then open air compressor air supply, and finally open the plug valve under the warehouse to feed.
4.2 Stop sequence: shut down the warehouse plug valve and stop the feeding. After the materials in the equipment and pipes are finished, shut off the equipment other than the air source. After ensuring that all the materials in the pipe are finished, shut off the air source.
1. Single-manipulation transfer: When commissioning or when it is not used for a long time, a separate test machine should be performed for each piece of equipment. The operating rules for stand-alone equipment are found in its instructions.
2. Air conditioning test: After confirming that each equipment is operating normally, it can be commissioned by the empty machine. The empty machine commissioning sequence is: the air compressor is finally opened, and all equipment is opened and the air source is opened.
3, with the material debugging: After the air conditioning test is normal, can only take the material test machine, the first small flow debugging, according to the situation slowly increase the flow, just start running, flow control in the design of 80%, wait for a period of time, all The equipment is adjusted to 100% after normal running.
4, operating under normal conditions
4.1 Starting sequence: From the discharge end to the feed end one by one, and then open air compressor air supply, and finally open the plug valve under the warehouse to feed.
4.2 Stop sequence: shut down the warehouse plug valve and stop the feeding. After the materials in the equipment and pipes are finished, shut off the equipment other than the air source. After ensuring that all the materials in the pipe are finished, shut off the air source.